NC-2009 EAc5:Measurement and Verification

Final M&V Report

We would like to know if the project can obtain its LEED certification prior to submitting the Final M&V Report, which is dependent upon 1 year of post-occupancy energy use data. Can anyone help me understand the timing of the building certification when there is an outstanding LEED submittal for this credit? Thanks.

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 02/26/2015 - 19:16

The submittal for LEED is the M&V plan. The final report does not have to be sent to USGBC.

Thu, 02/26/2015 - 20:11

Thank you Marcus! That makes sense and now we can proceed with confidence.