We would like to know if the project can obtain its LEED certification prior to submitting the Final M&V Report, which is dependent upon 1 year of post-occupancy energy use data. Can anyone help me understand the timing of the building certification when there is an outstanding LEED submittal for this credit? Thanks.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
February 26, 2015 - 2:16 pm
The submittal for LEED is the M&V plan. The final report does not have to be sent to USGBC.
Valerie Walsh
Sustainable Design & Construction ConsultantsWalsh Sustainability Group
219 thumbs up
February 26, 2015 - 3:11 pm
Thank you Marcus! That makes sense and now we can proceed with confidence.