CS-2009 WEp1:Water Use Reduction

CS project without bathrooms and elegible fixtures

We´re working in a CS building without plumbing fixtures. How we can document the WEp1?. We need to make the Tenant Lease agreement?, How we can earn points in WEc3?. We need to specify the future water fixtures in the form?. Thanks in advance.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 06/10/2015 - 21:38

I have the same question as Maria.

Mon, 11/30/2015 - 23:09

Hi Maria and Annalise, WEp1 and WEc3 are both "Case A" credits in the CS Appendix 4 of the Reference Guide, meaning that any performance based on anticipated tenant work outside the scope of the C&S project would need to be included in an agreement with the tenants. I've seen this requirement stipulated as either an overall percent reduction or as prescribed flow rates for each fixture.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.