We would like to know if it is possible to start the flush out (and maybe even finish it) before all permanent furniture is installed. The furniture is fabricated in a shop outside the site and free of urea formaldehyde.
Thank you.
Forum discussion
NC-2009 IEQc3.2: Construction IAQ Management Plan—Before Occupancy
We would like to know if it is possible to start the flush out (and maybe even finish it) before all permanent furniture is installed. The furniture is fabricated in a shop outside the site and free of urea formaldehyde.
Thank you.
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
July 26, 2014 - 8:32 am
Pascal, this is a complicated question that is answered thoroughly in one of our FAQs above, under LEEDuser's Bird's Eye View guidance.