I see some threads on this issue but want to re-open this conversation. We have CI projects that are in buildings that have executed leases with a 10 year duration. However, the projects are happening at different times during the duration of the lease. In other words, the renovation or build out of the space does not coincide with the beginning of the ten-year lease. Per Tristan's post of Dec 18, 2011, he believes that is the intent of this credit.
However, in the 2009 reference manual, it says "The credit requirements are satisfied when the project area is either owned by the occupant or is currently included in a lease with a term of no less than ten years." And then further, "The requirement does not stipulate a relationship between the start of the lease period and the project construction activities". These statements suggest to me the opposite.
Our projects are included in leases that have terms of no less than ten years, whether those terms started in 2007 or they started in 2013. Has there been a more recent addendum or LI that I missed that addresses this? Has anyone received review comments that clarify this issue?
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 4, 2013 - 10:40 am
Michelle, have you checked out LEED Interpretation #10052 (referenced above)? It adds a piece of clarificaiton to this puzzle.
Michelle Rosenberger
PartnerArchEcology
523 thumbs up
November 4, 2013 - 6:26 pm
Hi Tristan,
Yes, thanks. We have a lease, and its duration is 10 years. But our project TI construction is halfway through that 10 year duration period. Some of the answers below seem to indicate that you should be in the space 10 years after certification. As if duration needed to be coincident with the completion of construction. I will go with the reference manual statements above. Our project is included in a lease with a 10 year duration, and there need not be a relationship between the start of the lease and the construction activities. Thanks.
emily reese moody
Sustainability Director, Certifications & ComplianceJacobs
LEEDuser Expert
476 thumbs up
September 29, 2016 - 4:20 pm
Michelle, just out of curiosity, was your approach accepted by the reviewers?
Michelle Rosenberger
PartnerArchEcology
523 thumbs up
September 29, 2016 - 4:32 pm
Hi Emily,
Yes, it was. Duration of lease itself is the issue.