Our client’s CS-project has been denied EAc5.2 because we haven’t provided separate sub-metering of tenant lighting and plug loads. According to the review comment, separate sub-metering is required by LEED CI EAc3. Our project is Case 1 (less than 75 % of total area). Have I missed something here? The CI EAc3 credit language doesn’t say anything about separate sub-metering for Case 1 projects. Also, the Green Building Design and Construction Reference Guide (2009 edition) says clearly that for CS-projects, “electricity used for lighting and plug loads and to run HVAC equipment may be measured on a single meter and reported together”.