Healthcare-v2009 SSp2:Environmental site assessment

EA neccessary for existing developed?

The project is a complete interior overhaul of an existing building that had an office use, and turning into medical outpatient/medical office building, since the site was already developed on and assumed that the site was not contaminated is there a way around this prerequisite?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Sat, 08/24/2013 - 11:32

Nicole, Aside from the fact that there isn't any way to circumvent a prerequisite, I believe it is a mistake to "assume" the site was neither contaminated prior to the original construction, nor became contaminated post-original construction. Contamination could have migrated from off-site sources, through no fault, or knowledge, of the previous user.

Add new comment