NC-2009 EAc2:On-Site Renewable Energy

On campus PV towards EAc1

We have a client pursuing LEED NC certification for a new building that will be an addition to an existing building on their campus. They are currently in the process of installing a PV array on an existing garage in the campus. The PV array will be outside the new building’s LEED boundary and will be completed prior to the new building. A percentage or all of the solar power generated from the PV array will go towards the new building pursing NC certification. I understand that in such a scenario, if the PV array is under the same ownership but not within the LEED boundary, we can count it towards EAc2.In addition to the EAc2 credit, as this renewable energy helps offset total annual building energy use, can it contribute towards EAc1 as well? Also with regards to the requirement of not allocating the same solar power to another LEED project, in the future- would this apply to the building’s future LEED EB certification as well Thanks.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 07/16/2013 - 14:35

Yes, once allocated to the project by the owner, the renewable power can be used under EAc1 and for EBOM.

Fri, 05/24/2019 - 05:51

I have a similar situation. The owner has two adjacent bulidings, one of them will be LEED-certified and the other one will have solar panels but the energy produced will go to both buildings. Can I use some of the energy produced to earn a point in EAc-Renewable energy? The project will be certified according to v.4. Thanks

Wed, 05/29/2019 - 14:53

Yes you just have to allocate a portion or all of the production to your LEED project.