We have a construction site with an existing 40 ft asphalt driveway & entry/exit, which we will be using as our only construction entry point. Would an existing asphalt driveway qualify as legitimate sediment tracking solution, or will we need to provide crushed gravel/filter fabric or tracking mats?

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 06/04/2013 - 20:56

I've never seen this approach fly, unless you can make the argument that there will never be contact with disturbed soil.