NC-2009 EAc3:Enhanced Commissioning

CxA

If the task of CxA complete in design phase now for my building but the building construction will be finished totally after 4/5 years from now. In this case, will I face any problem to get the certificate from USGBC?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 07/17/2013 - 15:09

Jamal, your question is a bit confusing. If you are referring to the LEED certification for the building, under the LEED-NC system, you can only obtain that after substantial completion.