I am curious about the separate function AND ownership requirement for an addition to a non-certified building. We have several projects where we are adding to an existing building, and often the new addition is a wing or similar with the same function as the existing. Does this mean we essentially cannot submit it for certification? I have not had any experience where we're adding a new addition to a building and the addition has a different owner. We are doing as much as we can to differentiate the certified wing from the non-certified, but the "ownership" distinction is difficult for me to fathom. Any thoughts? Or is CIR always warranted?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 5, 2013 - 10:19 am
Jonathan, I hope this helps, belatedly. Given the far-reaching consequences of MPR2 on a project, I thinking that contacting GBCI to clear up any questions is often warranted, although a CIR may not be necessary.I'd love to take a stab at your question if you want to post about a specific instance. Or if you have had some insight since posting, please let us know!