My team and I are in the appeal phase for our project.
WEc3 was denied because the total area of exterior landscaping is 3,276 square feet, which is less than 5% of the total site area and therefore the project was not eligible for this credit.
The team wants to increase the exterior landscaped area to 4575.8 sf, making us eligible for the credit.
This landscaped areas will be modify now (as tomorrow), and we would like to know whether it is permissible to modify the landscaping, have a contract will an designer and have only 50% advance in the landscape project at the moment of submitting the appeal.
Would this be acceptable? Or the 100% of the project should be finished at the time of the final submittal?
Thank you in advance for any comments.
Trista Brown
Project DirectorWSP USA
456 thumbs up
July 9, 2013 - 5:28 pm
Hi Alicia,
Did the final review comments provide any instructions for an acceptable course of action in the event of an appeal? I recommend trying to contact GBCI about your proposed approach before you spend time and money modifying the site.
Trista
Lili Pan
LEED AP BD+C, O+M, Managing DirectorL GEES 智利捷达
1 thumbs up
October 12, 2013 - 10:36 am
Hi Alicia,
Interesting question and what is GBCI final review comment? Thank you!