If you are putting a Community Center and Fire Station Building on a site that is currently a portion of a park is that project exempt from the 'do not build on previous park land" criteria and therefore still eligbile for SSc1? The community center will be used/staffed by the park's department.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 2, 2013 - 11:37 pm
Paula, as stated in the credit language, "park authority projects and projects which are operated by and support the function of the park are exempt" from the park land requirement. It sounds like this is the case in your situation.