Healthcare-v2009 MPR3:Must use a reasonable site boundary

Project of 2 buildings in one territory

I am working on a project who has two buildings in his land, but only one of them (an office building) will be in the process of becoming LEED NC. Both buildings are sharing the same parking and entrance to the street. For the Erosion credit, as well as for the LEED site delimitation (we are also considering to maximize green spaces, etc) should I include all the project site or only delimited to the office building and a little bit around? Thank you for helping.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 04/30/2013 - 23:05

Laurence, although some of the details here are sketchy, based on what you describe, you would exclude the non-LEED building from your LEED boundary, and applicability for most LEED credits.For SSp1, it wouldn't really make sense to artifiically limit the ESC plan to the certified building—it would be relevant to the whole site.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.