CI-2009 EAc2:Enhanced Commissioning

CxA contract

Hi all, From the LEED Online form: "Upload EAc2-2. Provide the contract between owner and CxA ensuring CxA involvement post-construction." Would a contract between the LEED consultants and the CxA suffice instead of the contract stated above? Thanks in advance.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 01/08/2013 - 14:01

I do not see a problem as long as the contract path does not go through the Contractor. In other words, if the LEED Consultant has a contract to the owner it should be fine, I would just state that to the reviewers either by adding a note to the PDF or including the Owner to LEED Consultant contract along with the LEED Consultant to CxA contract.

Thu, 10/25/2018 - 20:17

Hi Scott! Do you know if a PO (Purchase Order) will be acceptable? (in lue of signed contract)