Hi All
When you register the project, does that mean that the time clock of performance period already starts ticking?
For example, Registration date = Jan 2012
therefore
PP = Jan 2012 - Dec2014?
then
certification application = Jan to Feb 2015?
Then certification application =
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
December 18, 2012 - 1:03 am
Mary Ann, the project registration date bears no relation to the PP dates. For example, you could register and submit for review on the same day, with the PP stretching BACKWARD two years.