EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy

How can the PV array benefit be shared?

Our campus has multiple buildings, one of which is going for EBOM now. The PV array is adjacent (in the parking lot). The PV's do have a meter, so we know their output. This output along with the local utility are like a pool, powering the entire campus. If we share the PV feature for LEED certification among all the buildings (using a sf allocation perhaps) the renewable energy to each building will be so low that no one will really get this EAc4, despite the millions of $ spent. What are our options?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 11/23/2012 - 20:38

Maria, you could allocate in LEED terms to one building to give that building EAc4. Or you could allocate it equally and make up the difference with purchases of RECs.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.