EBOM-2009 EAp3:Fundamental Refrigerant Management

DHC Plant with CFC refrigerant

Our project is served by district heat and cilled water plant. The plant, owned by different componay from our project owner, uses CFC refrigerant for some of chillers. It is difficult to do feasibility study for replacement of equipment by ourselves as well as to request the plant owner company to write a phase out plan. Is it possible for our project to meet this prerequisite requirement?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 10/16/2012 - 16:46

Per the District Energy Guidelines for EBOM, when a third party owns the district energy system, the EAp3 and EAc5 requirements apply to the downstream equipment but not the upstream equipment. So you're not obligated to try to convince a different company to change the way they do business with refrigerants. So, as long as you meet all of the EAp3 requirements for your own downstream equipment and make reference to the district energy guidelines, you will have the opportunity to meet this prerequisite. You can download a copy of the DES Guidelines for EBOM here: https://www.usgbc.org/ShowFile.aspx?DocumentID=8697

Fri, 10/19/2012 - 01:21

Let me ask one more question. Is it possble to pursue LEED-CI certification for future tenant to occupy the same building served by the DHC plant using CFC?

Fri, 11/23/2012 - 20:30

Noriko, I'm not sure I understand your question. Are you talking about a LEED-CI certification within the LEED-EBOM certified building? That would depend on the specifics.