Hello, we have recently realized that our project gross area was one number, and the energy model done by our engineer did not include an atrium space in the middle of the project (project is on 3rd floor with this space in the middle) nor did he include shafts, etc. We are in the appeals phase and do not want to change the project gross area at this point. Does his model need to match our project area or can we explain this and not get denied? Seems like they have been very picky with this and we stand to make Platinum. Thanks.