FAQs about EAp2 :

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

CS-2009 EAp2:Minimum Energy Performance

Fan Power Limitation Pressure Drop Adjustment

Hallo everyone, I am modeling a C&S project with 8 floors, and system 7 will be used in the Baseline Case. For system 7, usually each floor shall be modeled with a separate HVAC system in Baseline. But this project has both laboratory and office areas, laboratory spaces are smaller than office spaces and are more than 20,000 ft². Two separate AHUs supply outdoor air for lab and office. Therefore according to G3.1.1 Exception (a) I made also two HVAC in Baseline building. 1) Is this correct? 2) If this solution is correct, the pressure drop adjustment for fully ducted EA system is 0.5 or 0.5 x 8 floors? 3) Is there no pressure drop because of supply air ducts? Thank you in advance!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 06/15/2012 - 13:24

1. Sounds like you can apply that exception. 2. The pressure drop adjustment is applied to the fan power calculations at the system level. 3. I think it is assumed that the supply air is ducted, so no adjustment.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.