In the building we are modeling there are some technical floor among conditioned floors for example between the 9th and the 11 th floor which are conditioned there is a tehcnical floor which is neither cooled nor heated my questions are:
1- can I consider this technical floor as an attic above the 9th floor ?
2-DO I have to model it which means do I have to check the lights,glazing... or what else can i do?
3-what is the temperarure I should set to allow for heat transfer between conditioned spaces and this technical floors.

REgards,