FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

ASHRAE 90.1 does not apply to portions of Building

A portion of our new building will be dedicated to maintenance of large vehicles (large trucks, earth movers, etc) and is priimarily industrial in nature. These areas are provided with exhaust fans, but are not conditioned (no heating, no cooling, no indirect cooling). We are excluding these portion of the building from our simulation model based on the fact that ASHRAE 90.1 does not apply to equipment and potions of building sysems that use energy primarily for industrial, manufacturing or commercial purposes (ASHRAE 90.1 section 2.3.c). My questions are: 1. Do we need to include the power for the exhaust fans serving these areas in our model as process loads? 2. Do we need to include the lighting of these areas in our model? 3. If the lighting must be included, does it need to be treated as a process load, i.e. same in Baseline and Proposed cases, or can we use ASHRAE LPD for the Baseline case and the As-Design LPD for the proposed case?

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 04/25/2012 - 12:52

These areas should be included in your model. LEED has consistently applied 90.1 to building types for which the Standard was not written. Many manufacturing facilities have obtained certification. The credit language clearly requires that the model include all energy use associated with the building project, including all process loads. 1. yes 2. yes 3. Use the most appropriate ASHRAE LPD in the Baseline and the actual design in the Proposed.

Wed, 04/25/2012 - 18:45

Thanks for your response.

Add new comment