FAQs about EAp2 :

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

ASHRAE 90.1-2007 Lighting Power Density

Dear All, I have a doubt regaridng the LPD requirements for LEED projects. I am doing a Hotel project and would like to know if its mandatory to comply with Table 9.5.1 and Table 9.6.1 for LPD. Since this is a high end Hotel, I find it difficult to meet the above requirements in most of public and amenities spaces and its higher than the listed values. Do you know if there will be any issue with LEED certification if the 90.1 LPD limits are exceeded.?

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 02/14/2012 - 14:26

You only must comply with the mandatory provisions in X.4 of each section. So these tables and the LPDs are not mandatory.

Tue, 02/21/2012 - 10:08

Thank you so much Marcus..

Fri, 03/21/2025 - 17:57

Hi Marcus, Please allow me to revive Arub's original question. I have been working on high-end luxury retail project, under LEED ID+C (Retail) v4, pursuing EAp Prescriptive Compliance Path with LEED v4.1.  LEED v4 states, “Reduce connected lighting power density by 5% below ASHRAE 90.1-2010 using the space-by-space method or by applying the whole-building lighting power allowance to the entire tenant space.”, whereas LEED v4.1 states, “prescriptive provisions of Sections 5 through 10”. Here, my understanding is, a minimum reduction in connected lighting is not specified and therefore not required. Similarly, in Section 9 of ASHRAE 90.1-2016, only the mandatory provisions in Section 9.4 are listed in the ASHRAE Lighting Compliance Form. This means the project is not required to comply with Table 9.5.1 or Table 9.6.1. Am I correct to understand that complying with Section 9.4 would suffice, irrespective of the LPD? This question is crucial because it leads to make-or-break point where the project's LPD has far exceeded the prescribed limit of the ASHRAE, mainly due client's intention of making the space look grand. We sent several inquires to GBCI and strangly, received conflicting views on it. I would greatly appreciate your comment. Thank you in advance!

Wed, 04/02/2025 - 21:41

Please post this question in a LEED v4 or LEED v4.1 forum as no one will see the answer in a LEED 2009 forum.

Wed, 04/02/2025 - 21:45

Please post this question in a LEED v4 or LEED v4.1 forum as no one will see the answer in a LEED 2009 forum.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.