My project is registered under LEED CS v2.0, so the requirements may be a little bit different than CS v.3, however I hope you can still be able to help me.
If I understand corectly, this credit requires showing the locations of heating and cooling equipment (in my case thermostats and cooling beams) on the floor plan. How should I do it, if I'm certifying only core and shell spaces and I have no idea how the future tenants would like to design their premises. Shall I submitt a sample fit-out?
Thanks!
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
February 21, 2012 - 9:57 pm
Alicja, I am not familiar with CS v2, but in v2009, this kind of question is addressed in Appendix 4 in the LEED Reference Guide. Perhaps you could review how it is handled there and come up with an approach for v2.0.
Christopher Schaffner
CEO & FounderThe Green Engineer
LEEDuser Expert
963 thumbs up
November 25, 2012 - 10:29 am
Under CSv2.0 you are not required to show locations of heating and cooling equipment for this credit. A narrative and supporting calculations should suffice.