Dear all,
The LEEDOnline letter template for IEQc3.2 includes a portal to upload the IAQ Management Plan highlighting post-construction IAQ management practices.
Is this plan different from the one developed for IEQc3.1? My understanding is that either a flush-out or IAQ testing is required, with no need for producing any additional Management Plan.
Many thanks
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 11, 2011 - 12:27 pm
George, most teams that pursue both IEQc3.1 and 3.2 write one plan that covers both requirements. You can see an example of this above, in our Doc Toolkit. For more background on writing and submitting the plan, it may help to review the steps to earn this credit in the Checklists tab above.
Maya Karkour
EcoConsulting872 thumbs up
November 14, 2011 - 5:31 am
Thanks Tristan!
For the Pre-Occupancy Flush-out option, the LEEDOnline letter template asks for a description of the flush-out procedure (date, airflow rates, temperature, and humidity).
What is the difference between the content of this description paragraph and the "IAQ Management Plan highlighting post-construction IAQ Management practices implemented"?
Are there any post-construction IAQ Management measures other than the flush-out or the testing?
Thanks,
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 19, 2011 - 9:29 pm
George, to my knowledge there is not any difference, unless there happens to be something about the project that warrants note.
Denise Domino
DivisionOne Construction, LLC4 thumbs up
July 13, 2017 - 9:45 am
Tristan:
IAQ Mgmt. Plan - Post construction AND Post Occupancy measures
What are your options if neither Option 1 or 2 were done?
I know there is IAQ Testing after Occupancy but they do not think the testing will pass.
Are there ANY options here??