Our project team is working on LEED EBOM certification of an industrial compound, and there is a question we are not so sure about and we believe one of you may be able to help. The company which owns the compound we are working on has plans to install meters in the buildings located inside of it, to earn credit EA 3.2 – Performance Measurement: System-Level Metering. However, there are three buildings within the site, and we are wondering whether we will have to install sub meters for all main energy-consuming systems in each building or we can install general sub meters for the main energy-consuming systems of the compound as a whole (which would be easier). We are asking you this because each facility has its own energy distribution characteristics and we believe it will not be worth installing the 79 meters they calculate, for the costs they will pay. Is there any reasonable solution we can apply to earn this credit?