IEQp2 is a design prerequisite. For residential units, (smoking allowed), we have to upload blower door test results. Since it is in design stage, there is yet nothing to perform testing on. Do I write in special circumstances that I will upload results as soon as there are any, and submit at construction stage?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Susann Geithner
PrincipalEmerald Built Environments
1297 thumbs up
November 15, 2011 - 11:01 am
We did this before and submitted in design phase. The reviewer however does not approve it until you have the results. In our case it stated that our approach is ok, but we should submit the prerequ in construction review, which we do.
Maria Porter
Sustainability specialistSkanska Sweden
271 thumbs up
November 16, 2011 - 9:06 am
Thank you Susann!
We will have recieved a few results before we submit, but from all. So we will submit what we have and send in the rest at Construction Submittal. Apartments will be finished and moved in at different times (about once a month), during more than a year. It's a large building, a whole block.