Forum discussion

EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiency

Good or no?

The way I am interpreting this credit, it would seem that is the project was built post 1994, while a baseline can be calculated, there is no chance of not meeting the PR as long as a satisfactory maintenance plan is written and implemented. Is this correct? Also, must the plan be actually implemented or, as with the other PRs, is it only a plan that must be written? thanks for your insight!

5

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 07/20/2011 - 20:55

*if the project was built

Wed, 08/03/2011 - 15:07

That is correct - the EBOM template even provides a compliance path specifically for buildings constructed in 1993 and beyond. That being said, in my experience, however, its not uncommon to find higher-flow fixtures even in buildings built in the 1990s. And two important exceptions that remain commonplace are faucets and showerheads - the 2.2gpm faucet remains far more common than 0.5 gpm faucets, and showerheads are all over the map these days. But the answer to your question is yes - the prereq can be earned automatically. The expectation for the plan is indeed implementation, and I would caution the notion that other policies simply need to be written rather than implemented. For all prerequisite policies, LEED expects full implementation to the extent feasible. That doesn't necessarily mean a specific performance goal would be achieved, but it goes well beyond simply writing a plan and handing it over.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.