According to MPR 3 , 1. "The LEED project boundary must include all contiguous land that is associated with and supports normal building operations for the LEED project building, including all land that was or will be disturbed for the purpose of undertaking the LEED project".
This is an existing facility and there will be a building to retrofit. There is a parking lot right next to the retrofit; it will be used for materials stock, temporary workers constructions, and construction activities for the space to retrofit. Can I leave it out of the boundary? Technically I'm not disturbing the land, since this was a parking lot and still will be after construction.
Also it is not clear to me if including existing parking capacity is required, since there will be no new parking spaces, can I just draw my boundary around the building to retrofit??
Thanks
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
June 7, 2011 - 11:14 pm
Xavi, I assume the parking lot is used for the building under normal operations? If so, it should be included within your LEED boundary. Parking is considered normal operations relative to the MPR text you quoted.
javier bolanos zeledon
243 thumbs up
June 9, 2011 - 10:37 pm
Thanks Tristan. What if the parking lot we are using for materials stock is for the warehouse. And there is another parking lot for the office building. Can I leave it out of the boundary even thogh it's being used for the LEED project materials stock.
KC Kurtz
Designer-BuilderBuildsense + Studio B Architecture
11 thumbs up
July 12, 2011 - 3:14 pm
Tristan --
Thanks to you, and others, for the wealth of information on this site!
This is the first LEED project for everyone in my office and so this site
has really been invaluable to our, as yet, less-than-perfectly-coordinated
process. Thanks again.
This is a question in a very similar vein to Xavi's above, however, even
after reading the MRP Supplemental Guidance, I
am still unclear as to where I should draw my LEED Project Boundary
Here's our situation:
We own 2 urban properties separated by a city road.
The first property,
and the one that we will develop as our C and S LEED project, is an existing
one story building (former automotive shop). We are planning on
engaging in adaptive reuse, utilizing the existing brick perimeter
walls and steel structure, for the first floor (6200 sf), and adding a
second floor (5800 sf), to create a 12,000 sf (approximate) mixed
use office building. This property is mostly zero lot line with a small
amount (350 sf) of pervious area that will be landscaped.
The second property on the other side of the city street is a parking
lot that we do not want to include in our Project Boundary --
We hope to do a separate LEED NC project here (Alternative Fueling
Station) at some point in the relatively near future. Until the Fueling
Station project is complete (and potentially beyond that point) we will
use this property as parking for property 1.
A third property, which we do not own, is a parking lot and storage buildings,
and is contiguous to the first property (LEED project building).
We have permission from the property owner (also the owner who
sold us property 1 and property 2) to use the parking lot and
storage buildings to stage material and equipment during construction.
We will also place our construction dumpster/recycling in this parking
lot during construction and we will extend our construction fence
(chainlink) onto this property. After construction, we will not use property
three for any purpose.
OK - so here's my question:
Can we draw the Project Boundary around the Project Building (property
line) only or do we need to draw it around (and therefore include in
all related credit/prerequisite calculations and documentation) property
3 (temporary staging area that we don't own)?
Many thanks.
David Posada
Integrated Design & LEED SpecialistSERA Architects
LEEDuser Expert
1980 thumbs up
July 12, 2011 - 5:55 pm
It sounds like the third property is a previously developed, urban lot that is being used for temporary staging of construction activities, and is not a greenfield area that is receiving any site disturbance (as would be addressed by SSc5.1). If there are no permanent improvements to this area that will support the building on site 1, it sounds reasonable to exclude it from the LEED Site Boundary.
If the second property were to be redeveloped to provide permanent parking for the site 1 project, you would need to include it in the LEED boundary for site 1. If the local zoning requires you to provide parking, it seems like you'd have to include that area within your LEED boundary
If you are not required to provide parking, and If the second property were legitimately being used for only temporary parking for site 1, you might be able to argue it should be excluded from the site boundary, because it wouldn't be supporting the building, but then you could not use that area for any of the site credits such as SSc4.3 or SSc5 or SSc6.
GBCI gives project teams some latitude to define the boundary as they see fit, but if the parking is required it seems like you'd need to include it.
KC Kurtz
Designer-BuilderBuildsense + Studio B Architecture
11 thumbs up
July 13, 2011 - 9:15 am
Thanks for your thoughtful reply David - It was very helpful.
With regards to property 2 referred to above, I am basing my understanding of Project Boundary exclusion on four pieces of information:
a) MPR Language -- "The LEED project boundary must include all contiguous land that is associated with and supports normal building operations for the LEED project building, including all land that was or will be disturbed for the purpose of undertaking the LEED project".
This parking lot is not "contiguous" to our LEED project building, but rather, it is separated by a city street (public right-of-way).
b) MPR Supplemental Guidance Revision #1 -- "When non-contiguous parcels [MAY] be included within the LEED project boundary: Non-contiguous parcels of land [MAY] be included within the LEED project boundary if the conditions below are met, and at the [PROJECT TEAM'S DISCRETION]...."
The "may" and "discretion" language implies to me that the corollary would also be true -- we may also choose NOT to include this non-contiguous land within the LEED project boundary.
c) Also, our local zoning does not require parking for this property - we are considered "Downtown Exempt".
d) It was also encouraging to hear, from you, that GBCI "gives project teams some latitude to define the boundary as they see fit...".
Also, as mentioned in my first post, we are considering developing this parking lot, using LEED NC, as an alternative fueling station (biodiesel, cng, and electric plug-ins), at some point in the future.
So, all this being said, I'd love to get a follow-up response from you on this issue of project boundaries.
Thanks again for your help!
David Posada
Integrated Design & LEED SpecialistSERA Architects
LEEDuser Expert
1980 thumbs up
July 18, 2011 - 7:22 pm
KC,
I'd agree that the lack of a parking requirement and the MPR language on page 23 of the new guidance that says "may be included" and "at the project teams discretion" suggests you some latitude here to draw the boundary as you see appropriate. (Also check the conditions for exclusion at the top of pg 24.) I can't say for sure how a reviewer will interpret the MPRs, but your approach seems reasonable.
KC Kurtz
Designer-BuilderBuildsense + Studio B Architecture
11 thumbs up
July 19, 2011 - 7:41 am
Thanks, David - fingers crossed....