Commissioning process in a volume program

After reading the documentation about the LEED Volume program, I understand that it is essential to implement a quality control plan in order to ensure that the certified prototype will be implemented consistently. Thas is very similar to the objective of the commissioning process, althout on a larger scale. My question is : Is it necessary to implement a commissioning process everytime there a store is build, or is commissioning integrated in that overall quality control plan?

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 03/22/2011 - 17:29

Emmanuel, if I understand your question correctly, every building must be commissioned to comply with EAp1 and EAc3, if EAc3 is being pursued.