We are considering three Innovation in Design credits for a supermarket in LEED 2009 for Retail: a Food Donation program to reduce solid waste; an in-store and online Education program; and a Green Cleaning program. Which of these would be considered Design Phase submittals, and which would be Construction? Thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
February 18, 2011 - 2:27 am
Lewis, it depends on the details but I would think they could all be submitted under a Design submittal. This is beneficial in that you can make adjustments to them for the Construction submittal if they are not accepted.