Hi all,
For a data center that is equiped only the first 2 storeys out of total 5 storeys for the first few years, how should the energy calculation be done? should I include energy consumption of the other storey as well or only the 2 storeys?
Thanks a lot.
Christopher Schaffner
CEO & FounderThe Green Engineer
LEEDuser Expert
963 thumbs up
January 3, 2011 - 10:31 am
You need to model the entire building, as though it were completely occupied. "Future" lighting and process loads should be identical in each case.