If you are enhanced commissioning a building, are you required to wait until the 8-10 months for the operation review, in order to submit the documents to GBCI?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
November 16, 2010 - 11:59 am
No, you're committing to following through on that but you submit the required documentation along with all other documentation for the final review.