My inital thought is that you are infiltrating the entire volume within your LEED boundary (I assume) and if this is the case, then your run-off flow rate is also zero. You only need to measure the rate and volume as it leaves your site.

Wed, 10/13/2010 - 16:59

Gregory, Thank you for the response. That was what we decided to do until we heard opinions otherwise. Our Post-development Rate and Quantity are now set to zero. The form allowed this and allowed us the point.