Forum discussion

ESC vs SWPPP

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 05/13/2010 - 22:53

Josephine, This is two-fold in a way. You must comply with the EPA’s Construction General Permit AND make sure that the ESC covers prevention of topsoil loss, sedimentation in receiving streams and of air pollution by particulate matter. My understanding is the portion related to dust control is left to the project civil engineer to determine what is most appropriate for the site. I hope that helps. Shannon