Sorry, not sure why I got all the weird scripts before my message, I copied /pasted the comment.. Please read starting from "Appendix 4".
Thanks,
Maya
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Ben Stanley
Senior Sustainability ManagerWSP - Built Ecology
LEEDuser Expert
250 thumbs up
January 29, 2010 - 2:01 pm
Maya,
I would interpret the information in Appendix 4 Case C to mean that your team would be required to ensure ETS separation according to Case 1 Option 2 via a legally binding agreement with the building tenants.
V. Miller
WSP78 thumbs up
May 20, 2010 - 7:49 am
Appendix 4 is not clear on whether tenant spaces need to comply with ASHRAE 90.1. Please clarify.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
May 26, 2010 - 3:41 pm
Tenant spaces would only be required to comply with 90.1 in so far as their space was completed within the core & shell scope. Any tenant fit-out remaining after the core and shell was complete wouldn’t be required to meet 90.1.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
November 13, 2010 - 11:54 am
I don't have direct experience with this, so I have to make that caveat.But according to my reading of CS Appendix 4 and my general understanding, it's not referring to a path for ID points or even a substitute, it's referring to a compliance method for regular credits. In cases where compliance with the credit would rest to significant degree on what the tenant does, binding language directing them to meet the LEED-CS requirements would be accepted as documentation for the LEED-CS credits.One exception to what I just said—at the end of the appendix, there is a note about how EP points can be earned through some specific credit paths.
Carolina Vergnano
LEED APConcremat
145 thumbs up
April 14, 2011 - 4:16 pm
Tristan,
We are having some problems with a client that do not want to certify LEED-CI its interiors and leased a floor in a LEED-CS certified building.
The owner is requiring that the projects comply with ASHRAE what is increasing a lot the project budget and our client do not have enough money. Does owner impose us to meet ASHRAE 90.1? As per your previuos comment we understand that he can not.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
April 22, 2011 - 6:58 pm
Fabiano, read CS Appendix 4 and tell me what you think. It appears that you must include tenant space in consideration for EAp2 for CS projects. This implies some control over what the tenant does in their space relative to ASHRAE 90.1, etc.