Schedule the installation of absorptive composite materials so that they are protected from construction air contaminants. This is required if projects are attempting EQc3.1: Construction Indoor Air Quality Plan—During Construction, but is a good practice

Schedule the installation of absorptive composite materials so that they are protected from construction air contaminants. This is required if projects are attempting EQc3.1: Construction Indoor Air Quality Plan—During Construction, but is a good practice in any case. For example, storing or installing composite wood cabinets before wall painting can cause them to absorb the paint’s off gases and contaminate the air over a longer time period.