posted by  Kristopher Lashley  on 

We have a multi story underground parking structure that is exhausted with 26,000cfm P1, 32,000 cfm for P2 and P3.

0

Emergency generator fule meter

CI-2009 EAc3:Measurement and Verification
posted by  Edwin Wealend  on 

Hi we have a LEED CI project that is served by an emergency back-up generator that serves multiple floors. Is it really a requirement to meter emergency back-up generator fuel?

1
Tue Jun 2, 2015, 2:06 pm

measuring heat pump load for system submetering

EBOM-2009 EAc3.2:Performance Measurement—System-Level Metering
posted by  ethan adams  on 

I have about 35 ceiling- mounted heat pumps throughout the building, and it would be cost-prohibitive to install a separate meter on each one.

1
Mon Nov 30, 2015, 8:16 pm

Confirmation - perforated sticker sign

CI-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Ian McCall  on 

Hello, Can someone confirm that an temporary (3 months) publicity perforated window decal installed by the future tenant on the glazed facade is out of the scope of the LEED NC or CS certification

1
Wed Jun 3, 2015, 5:49 pm

Credit Interpretation Request to support SS p1.

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Marie-France Duthilleul  on 

When comparing your proposed ESC PLan Is there standard text language / narrative that clearly describs the requirements of Phase 1 and Phase II of the NPDES program.

0

Data Center PUE & Energy Star Rating

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Charalampos Giannikopoulos  on 

Is there a correlation of PUE (Power Utilization Effectiveness) and Energy Star rating?

1
Thu Jun 4, 2015, 2:42 pm

Resilient Design

NC-2009 IDc1:Innovation in Design
posted by  Deborah Lucking  on 

We are required to address resilient design (e.g. against sea level rise, storm surge) in our project. Does anyone have any experience or words of advice about this? Thanks!

1
Thu Jun 4, 2015, 5:50 pm

20 or More Basic Services - Innovation Credit?

CS-2009 SSc2:Development Density and Community Connectivity
posted by  Ian McCall  on 

Hello, Is it possible to get an innovation credit for projects that have 20 or more basic services (that are different)? Regards, Ian

1
Thu Jun 4, 2015, 11:44 am

Greenroof, water retention with perlite

NC-2009 WEc1:Water Efficient Landscaping
posted by  FABIO VIERO  on 

I was wondering if anyone had already used a roof garden including the perlite. Perlite is a volcanic rock effusive varying in color between gray and pink, whose chemical composition is similar to

1
Mon Jul 27, 2015, 9:20 pm

Typical Days of Operation for a Combo Research & Classroom bldg.

Calculating FTEs
posted by  Joyce Kelly  on 

Typical days of operation for the students, professors & educational staff is 206 and typical days of operation for the researchers and associated staff is 260.

1