Natural System Instead of Public Sewer.
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by JOSE R. TAGLE on
Hi everyone! We are working on previously undeveloped land project, which apply for case 1 “site with existing imperviousness 50% or less”.
No irrigation, No landscape - option 2 compliance
NC-2009 WEc1:Water Efficient Landscapingposted by Nicole Kimoto on
I'm working on a project where the existing site is 100% concrete paving. We are not providing any landscape, thus no irrigation. Does this mean we comply with option 2?
RockWool MR6
NC-2009 MRc6:Rapidly Renewable Materialsposted by Al Shadid on
Is rockwool considered a rapidly renewable material? I understand that rapidly renewable materials must be made from either plants or animals and must have a harvest cycle of 10 years or less.
2 separate CI spaces, 1 project?
CI-2009 MPR2:Must be a complete, permanent building or spaceposted by Charles Nepps on
I am working on a project where we are doing TI work on two different flloors, of the same building, for the same tenant. Can this be treated as 1 project for CI 2009 certification purposes?
Hello,
We have a previously
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by Magda Aghababyan on
Hello, We have a previously developed project that does not meet the site area for protect and restore habitat.
LEED NC - Project Boundary
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by sompoche sirichote on
We are working on a project that consists of 2 buildings: office building and workshop building.
Rating System?
NC-2009 PIf2:Project Summary Detailsposted by Racha Rachwan on
I'm working on a project containing one Basement, Ground and a first floor, it is a residential building, its building footprint meets the minimum program requirement.
CO2 in tenant spaces with visual alarm system
CS-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Jatuwat Varodompun on
It seems that scop of CS does not require CO2 sensors to be placed in tanent space.
VRP calculations for fan-powered boxes using 62MZ calc
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by tiantian zhou on
Our system has fan-powered VAV boxes. The first review comments required us to use 62MZ calc to account for local recirculation. But we have 120 AHUs and hundreds of zones.
Late involvement by CxA.
CI-2009 EAc2:Enhanced Commissioningposted by Charles Nepps on
The Owner dragged his feet and did not bring a Commissioning Agent on board until after the construction documents were complete, and construction started.