Healthcare-v2009 IEQc2:Acoustic environmentposted by BABAR MEHMOOD on
What i understand from this credit is it has 2 portions. On is regarding the sound isolation alongwith the room noise and additional points will be given if comply with the acoustical finishes.
2 options, Flush out and Air testing
Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Yazmin Trueba on
230k School, Tight Schedule, Path 1 Flushout before occupancy, Per Phases, 21 Air Handler Units / Zones, 6 areas of Flushout durations from 99 days to 30 days. My questions: 1.
CHANGING FIXTURES TO MEET PREREQUISITE
EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Daniel Rohe on
I have a building that was built before 1993 with airators that are 2.2. Inorder to meet the prequisite I have to change the Airators to .5.
Occupancy for the calculations
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Patricia Fuertes on
Good afternoon, I have a question about the occupancy I have to take into account for the minimum air flow calculations.
Blower Door Testing on 36 Story Multi-Family
EBOM-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Rachel Shepherd on
I am working on a project where blower door testing is required for a multi-family facility. The building is 36 stories tall with a mechanical penthouse.
SSc1 Path 7 Water Efficient Landscaping
CI-2009 SSc1:Site Selectionposted by Brian Kelly on
We are doing a renovation on a hospital in Las Vegas NV. The hospital has two very small patches of landscape that use what we believe to be an efficient irrigation system.
Calculating "Projection Factor" for curtainwall shading devices
CS-2009 EAp2:Minimum Energy Performanceposted by Amit Ahiel on
I'm working on a project where part of the curtain wall has a few random horizontal elements that project from the vision panels from floor to ceiling. These elements provide shading and therefor
Commissioning Services Contracted Through Design Firm?
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jaclyn Whitaker on
We've just received an RFP for a new project instructing my firm to provide fees for LEED Administration, Energy Modeling and Commissioning.
Parking Lots count as open space?
CS-2009 SSc5.2:Site Development—Maximize Open Spaceposted by Ioannis Rizos on
We have a shopping center located in an semi Urban area, in which there is no local zoning requirement.
Plastic chute for debris management
CS-2009 MRc2:Construction Waste Managementposted by Antonio Rodriguez on
Our project is a 40-story building, and we are having a hard time managing the debris and garbage produced in superior levels, in order to carry it all the way down to street level, so that it can