I have a building that was built before 1993 with airators that are 2.2. Inorder to meet the prequisite I have to change the Airators to .5. Can I just go ahead and change them out and then submit for approval. Or do I have to report as is, make a plan to conform, and then change them?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Trista Brown
Project DirectorWSP USA
456 thumbs up
May 8, 2013 - 9:54 am
Hi Daniel,
You can change out the aerators and complete the credit form using the 0.5 gpm flow rate.