Forum quick links
Tenant Submetering connected to BMS?
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Marco Abdallah on
We are pursueing 5.1 Opt. 1 and 5.2 at a CS-project with 10 floors leasable to different tenants.
Pond use outside LEED boundary
CS-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Brian Wolfe on
Is it acceptable to utilize an existing detention pond that is outside the proposed LEED boundary? The stormwater runoff will be piped under the existing road to the pond.
Lighting measurement
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ron Dean on
good day, I have a project with 14 floors and our project scope is to control the hall and restroom lighting, we can measure and verify their savings. I have a doubt about what I need to measure, m
Time Effort required for LEED ND Consultancy
posted by Mario S. on
Hello everyone, I am curious to know the following: Based on your experience dealing with large projects applying for LEED ND Certification, what would you say is the time effort per stage require
Green roof claimed through tenant lease?
CS-2009 WEc1:Water Efficient Landscapingposted by Dan LeBlanc on
Anyone know if a green roof with compliant irrigation systems can be required in a tenant lease to claim at least 5% of site area to achieve this credit?
Anyone tried using Wegowise for this?
Pilot-Credits PC38:Advanced Utility Trackingposted by Nadav Malin on
I just saw the announcement that Wegowise is offering a one-year trial to LfH certified projects. Has anyone tried it? https://usgbc.wegowise.com/
What is "flooring?"
CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elementsposted by Michael Smithing on
The space our CI project will be occupying currently has a raised floor installed throughout.
Ductwork Cleaning Standards
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Candice Rogers on
My Mechancial Contractor for a project submitted an IAQ Plan referencing the National Air Duct Cleaning Association's procedures for cleaning ductwork. I know that the IEQc3.1 is based on SMACNA.
Part II Multiple Buildings funcitonality
posted by Karen Joslin on
This is Q3 2012 and we still don't see the option for Part II projects at LEED Online?