Should I include the club space in daylight simulation?NC-v4 EQc7: Daylightposted by Agnieszka Kaczmarek on Jan 2, 2019, 7:57 am
On level -1 the club space is projected. According 'regularly occupied space' definition the club space is a an area where people spend more than one hour per person per day on average but the... |
|
C&S OccupancyCS-2009 IEQp1: Minimum indoor air quality performanceposted by Paula Hernandez on Jan 3, 2019, 8:29 am
Hi, We are working on a C&S project. We know that the spaces on the Ground Floor will be Restaurants and Sales spaces. For being a C&S building all the floors are now open... |
|
ID for smog sensors and anti-smog masksNC-2009 IDc1: Innovation in Designposted by Natalia Kwiecinska on Jan 3, 2019, 9:00 am
Our project is a hotel located in the city with huge problem with air pollution-smog. During 76 days in the year, the concentration of PM10 in the air is over the permitted limit. This is the... |
|
Category for Electrical Equipment Rooms in ASHRAE 62.1- 2010EBOM-v4 EQp1: Minimum indoor air quality performanceposted by SAMY Chamy on Jan 4, 2019, 5:02 am
I'm confused to what space category I should enter for Datacenter space which includes server racks under ASHRAE 62.1 - 2010. Under ASHRAE 62.1 - 2007, There was a space category 'Electrical... |
|
Changes in the LEED v4.1 BD+C draft to the Option 4 WBLCA- positive, overallNC-v4 MRc1: Building life-cycle impact reductionposted by Panu Pasanen on Jan 7, 2019, 2:22 pm
As most will have noted, the language for the v4.1 BD+C draft came out just before holidays. There are quite a few changes. The credit value is no longer fixed three points, but ranges... |
|
Condensate to a campus grey water system instead of being used on-siteNC-2009 WEc2: Innovative Wastewater Technologiesposted by Bo White on Jan 9, 2019, 2:16 pm
Our building is on a college campus and we plan to route all condensate to the campus grey water system. Does this qualify even though it is not being used on-site? Also, does condensate need to... |
|
Mastersite CalculationsCS-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by Ernst Schriefl on Jan 14, 2019, 5:10 am
Hallo, my project consits of 7 Buildings, whiche are certified under one Mastersite. Because of this i have serveral questions: Some of the buildings are greater then 300000... |
|
EA Prerequisite: Energy PerformanceLEED v4.1 Discussion Forumposted by Cesar Ruiz on Jan 14, 2019, 2:53 pm
I have noticed that in LEED OM v4.1 prerequisite Energy Performance the explanation about calculating the outside temperature adjustment factor is incomplete. This problem happens in both the... |
|
NC-2009 WEc1- Water Efficient LandscapingNC-2009 WEc1: Water Efficient Landscapingposted by ayda nezhad on Jan 17, 2019, 11:13 am
Hi, When we calculate the total irrigation design case(L) , is this volume per month or per day? |
|
DX unit fan cycling with occupancyNC-v4 EQp1: Minimum indoor air quality performanceposted by Saif Alsaeed on Jan 17, 2019, 6:05 pm