My project only has scrubs sink, which are exempt from LEED water use reduction requirements. The other portion of my project is undetermined, future fit-out space. I have calculated the NTE's using the CS Appendix-1 and have those numbers. However, part of the the credit form requires completing a fixture schedule. How does future fit-out space addressed for this credit? It is not designed so we cannot complete the fixture schedules as we do not have the fixture types selected. Do we complete the schedule with assumed fixtures...even though we don't know what the final number and type will be?