Plastic Cement Welding & PVC Welding

CS-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Lilian Seow on Jan 20, 2015, 3:19 pm

Page 509-LEED Reference Guide 2009-...

Last reply: Jon Clifford, Jan 21, 2015, 7:14 pm

Mechanical Ventilation using local code

NC-2009 IEQp1: Minimum indoor air quality performance
posted by MOHD HAFIZI MOHAMAD on Jan 20, 2015, 11:03 pm

Hi.

Is it a compulsory to design mechanical ventilation by using local code even if ASHRAE Standard is more stringent in order to score IEQ Credit 2: Increased Ventilation?

I got a...

Last reply: MOHD HAFIZI MOHAMAD, Jan 21, 2015, 9:37 pm

Advanced Buildings™ Core Performance™ Guide for residential

ND-v2009 GIBc2: Building energy efficiency
posted by Lise Dannesboe on Feb 1, 2015, 4:23 am

Hi!
Am I right that there is no prescriptive option available for residential multiunit buildings of more than 4 floors?
I understand that the Advanced Buildings™ Core Performance™...

Last reply: Casey Studhalter, Feb 12, 2015, 10:26 am

Calculation for Design Energy Cost

CS-2009 EAc6: Green Power
posted by Saud Abdul Rasheed on Feb 4, 2015, 2:29 am

Dear All,

We want to buy RECS for our project but I am confused about the quantity to buy. We performed an energy model and the total electricity demand for the project is 4,000,000...

Last reply: Marcus Sheffer, Feb 4, 2015, 5:02 pm

LEED Online v4 for Multiple Buildings on a Campus

LEED Guidance for Campuses and Multiple Buildings
posted by Deborah Lucking on Jun 4, 2015, 5:57 pm

LEED Online v4 was a surprise in more ways than one.
The individual projects are now certified under the Master Site, which is certified under the Campus (the old "block").
All well...

Last reply: Eric Anderson, Jul 20, 2015, 2:32 pm

Exceptional calculation method application.

NC-2009 EAp2: Minimum Energy Performance
posted by FABIO VIERO on Jun 8, 2015, 4:07 am

Under ASHRAE 90.1 – G2.5, can we avoid to use a workaround to detail a HVAC system feature which could involve an energy saving, therefore avoid to do an exceptional calculation method, if we...

Last reply: Marcus Sheffer, Mar 28, 2024, 10:00 am

Option 2 Calculation Question

NC-2009 MRc5: Regional Materials
posted by Haley Duncan on Jun 8, 2015, 2:41 pm

When calculating distances from location of extraction and location of manufacturing to project site, is it "as the crow flies" or actual travel distance?

Last reply: Jon Clifford, May 6, 2016, 10:09 pm

walk-in closets in residential

NC-2009 IEQp1: Minimum indoor air quality performance
posted by Alfonzo Collins on Jun 10, 2015, 4:32 pm

I would like to know if there's any way I can consider walk-in closets in a residential building as unoccupied spaces. The IEQ Space Matrix lists them as occupied, but this seems silly, since...

Last reply: Andrew Mitchell, P.E., Jul 19, 2017, 10:36 pm

Signed Contract with the CxA

NC-2009 EAc3: Enhanced Commissioning
posted by Mohamed M. Abd Elhameed on Jul 1, 2015, 4:22 am

We are pursuing LEED Certification for a 476921.20 sq ft Mixed Use Office Building in Egypt.

Building Owner is a multinational design firm who do both tasks, the project design and the...

Last reply: Scott Bowman, Jun 30, 2016, 4:51 pm

Laminating adhesives in composite wood assemblies

NC-v4 EQc2: Low-emitting materials
posted by Craig Graber on Jul 1, 2015, 2:46 pm

Does the "...

Last reply: Michelle Rosenberger, Dec 14, 2018, 6:05 pm