Log in
Forum
Topic

Minimum threshold for projects with new areas and existing areas

CS-2009 EAp2: Minimum Energy Performance
posted by MARCIO OROFINO on Jul 7, 2014, 5:15 pm

We have a project which qualifies for CS and can be treated as a single building. It is comprised of near 214,180 ft² that will be completely renovated (HVAC and other systems, except the...

Last reply: Marcus Sheffer, Jul 11, 2014, 11:21 am

Glazing location for visual access

NC-2009 IEQc8.2: Daylight and views - views
posted by SSN Energy Model on Jul 8, 2014, 3:17 am

One of our project (office building), sill height of the glazing is 6.5 feet from finished floor level & glazing height is 3.3 feet.
All the regularly occupied spaces are having...

Last reply: Jill Perry, PE, Sep 3, 2014, 2:42 pm

Natural gas use less than 1MMBtu...can't obtain carbon offsets

EBOM-2009 EAc4: On-Site and Off-Site Renewable Energy
posted by Wendy Parker, LEED AP on Jul 16, 2014, 2:20 pm

We have purchased our...

Last reply: Wendy Parker, LEED AP, Jul 17, 2014, 3:00 pm

Seasonal Commissioning

CI-2009 EAc2: Enhanced Commissioning
posted by Akos Brandecker on Jul 17, 2014, 10:44 am

Does the seasonal...

Last reply: Scott Bowman, Jul 23, 2014, 1:07 pm

LEED AP BD+C V4

General forums
posted by Marie-Pierre Pare on Jul 19, 2014, 8:34 pm

Dear Tristan,

I did the LEED Green Associate exam right before the change of version. I have only used one book to study (Gang Chen).

I am now ready to study for the LEED AP BD+C...

Last reply: Jeffrey Ornstein, Dec 20, 2014, 1:43 am

EP- Measure 4

CI-2009 IEQc8.2: Daylight and views - views
posted by Dennis Park on Jul 21, 2014, 6:59 pm

Is this measuring that 90% of spaces simply have access to views with a view factor of 3? For instance you will get credit if you are able to walk to a position in the room that allows you to...

Last reply: James Bell, Apr 4, 2017, 5:25 pm

Portland Cement

NC-2009 MRc5: Regional Materials
posted by Rezkar Abdulmajeed on Jul 22, 2014, 3:17 pm

Hi,

There is two methods of transport for the Cement I use for concrete in my project; It is coming by water to the port from an approximate distance of 2100 Km and then shipped by truck...

Last reply: Jon Clifford, Jul 25, 2014, 10:28 am

Discomfort hours- system 4

NC-2009 EAp2: Minimum Energy Performance
posted by Isabel Santos on Jul 23, 2014, 10:12 am

Dear all,
my building is a warehouse with 3 office areas that, for now, have no hvac system. However, since they are considered a conditioned space, I have to model a hvac system, the same...

Last reply: Isabel Santos, Jul 24, 2014, 2:50 pm

lab sink, kitchenette sink and shower water calculation rate

NC-2009 WEp1: Water Use Reduction
posted by ebru unver on Jul 23, 2014, 11:10 am

We are working on NC Office Building Project.
The building has 6 lab sinks, 3 kitchenette sinks and 9 showers (for guests, will be used maybe ones a week).
Should we include to the...

Last reply: Charles Nepps, Aug 1, 2014, 9:41 am

Kindergarten restooms w/ no occupancy sensor-OK or huge problem?

NC-2009 EAp2: Minimum Energy Performance
posted by Kathryn West on Jul 23, 2014, 2:39 pm

discovered a potential oversight on a building design: some restrooms intended to be used by very small kids are equipped with light switches and no occupancy sensors.

This appears to put...

Last reply: Marcus Sheffer, Jul 29, 2014, 3:39 pm