Task light process load or lighting load?
NC-2009 EAp2:Minimum Energy Performanceposted by Haojie Wang on
I saw some people say task light is process load but sometimes it can be count into lighting power. I wonder is there a good way to treat task light?
Option 3: Determining HC and NOx emissions
EBOM-v4 SSc5:Site managementposted by Michelle Raigosa on
Although an Equipment Emissions Reduction Calculator is provided, how do we address maintenance vehicles used on site?
Information on denied credits?
posted by Stephen Buonopane on
Has USGBC/GBCI ever published any studies of denied credits? Typical total number for a project?
3 glazed panels - LEEDv2009
NC-2009 IEQc8.2:Daylight and Views—Viewsposted by LEED Pro Consultant on
Hello, We have a layout configuration in which working spaces (offices) have glazed panels, allowing views to the exterior through other spaces that include also glazed panels.
LEED boundary for a railway station
NC-2009 PIf1:Minimum Program Requirementsposted by Juan Sergio Simborio on
LEED NC 2009 Our project is a major railway station in Qatar.
WEP1 for A project in Middle East
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Ayda Sahaf on
The project I am working on is an office building located in middle east. the Washroom water closets all has water jets or a bun gun fixture for washing purpose instead of using toilet paper.
Acceptable methods of Glare Control
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Paul Rogers on
I know that glare control is a requirement for each window.
Bicycle & Changing rooms in basement , 200 yards
CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Deepika Parmar on
Our project consists of three buildings connected through the basement and is registered under campus development. We are providing bicycle racks and shower changing rooms in the basement.
High-Volume vs. Convenience Copier 5,000 pages - CIR 872 Canada
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Lindsey Kindrat on
Heads up for those working on LEED Canada NC 2009 projects, CIR 872 ruled 5,000 pages per month as the definition limit for a convenience copier. Ruling provided 2012-06-08.
District virtual rate:
NC-2009 EAp2:Minimum Energy Performanceposted by Haojie Wang on
We have project using district steam. We use DES v2 to calculate the virtual rate based on state averaged electricity (0.084$/kWh) and gas (0.00757$/MBTU).