Major refurbishment - existing building
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Alicia Freire on
Can this credit not be achieved in an existing building where one floor (not the top floor) is being assessed and the existing roof will be left untouched?
Labs21 Issue
EBOM-2009 EAp2:Minimum Energy Efficiency Performanceposted by Eddie Cuevas on
I am working on a LEED-EBOM project that does not qualify for a Portfolio Manager rating due to the fact that lab space makes up more than 10% of the building area.
definition of 'mixed use'?
NC-2009 PIf2:Project Summary Detailsposted by emily reese moody on
Hi, We have a CS project that will have retail space on the ground level floor, and office space for the rest of the building.
Area calculation for trees
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by Muhammad Faisal Azizullah Jaffar on
I have a project where trees, shrubs and groundcovers will be used. While the area coverage of shrubs and groundcovers is relatively easy to calculate, trees are a bit more tricky.
Calculating materials costs to achieve MR credits
NC-2009 MRc3:Materials Reuseposted by Remigio Antonio Rancan on
Hi all, i don't find Table 2 indicated in LEED reference Guide for green BD+C p. 337. Can anyone help me? Thanks a lot.
N, Qunit (tons) and Refrigerant Charge (Rc) in lb/ton
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Adi Negara, LEED AP BD+C on
Dear All, I'm trying to fill the EAc4 form, but I don't understand about HVAC&R at all. I'm not too sure what is N, Q and Rc column meaning.
Can gas metering only qualify for EAc3.2?
EBOM-2009 EAc3.2:Performance Measurement—System-Level Meteringposted by James Doyle on
Under LEED EBOM 2009 I am considering attempting metering under credit EAc3.2 for a 200,000 sq. ft.
Residential Kitchen Equipment
Healthcare-v2009 WEc4.3:Water use reduction - food waste systemsposted by Rosemary Ziemann on
If the project is using residential grade kitchen equipment (this is for a licensed Nursing Home) - therefore we do not have a food waste disposer systems or pulpers, extractors, etc.
Systems Manual for Enhanced Commissioning
NC-2009 EAc3:Enhanced Commissioningposted by Tom Nichols on
We received a comment that we need to include system single-line diagrams in our systems manual. Can anyone clarify what the GBCI wants?
Option 2 documentation?
NC-2009 MRc5:Regional Materialsposted by Erica Downs on
Has anyone received any feedback yet on Option 2 documentation?