Post a question or comment
Location Filters
Filter by location
Forum
Topic
Replies
Recent

Mandatory 18% energy saving after April 2016

NC-2009 EAc1:Optimize Energy Performance
posted by  Indochine Engineering VN  on 

Hi, I just read requirement of EAc1 on USGBC web page, is it true that all LEED New Construction projects registered after 8 April 2016 have to reach 18% - 4 points at minimum.

5
Tue Aug 16, 2016, 3:16 pm

Broken Bricks, Tiles and waste materials

NC-2009 MRc3:Materials Reuse
posted by  Yusuf Turab  on 

We have used large quantities of waste materials procured from manufacturers. We have procured waste material like broken bricks form the brick manufacturer.

3
Managing Director
InHabit & BuildScape
LEEDuser Basic Member
18 thumbs up
Mon Aug 8, 2016, 1:05 pm

Tenant is installing the entire energy systems at the building

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Michael Wahjudi  on 

Hi all, we have building where the tenant is installing the entire energy related system (ACMV, lighting, etc). The landlord only provide land and structural of the building.

3
Fri Aug 5, 2016, 10:43 pm

Two buildings connected by a bridge

NC-2009 MPR4:Must comply with minimum floor area requirements
posted by  Eric Bautista  on 

My apology for posting a query quite not related to this section. Can I register a project consisting of two (2) identical buildings connected by a suspended bridge and both located within the dec

3
Head of Energy & Environmental Management
EB Project Management | Green Building Consultants
LEEDuser Basic Member
14 thumbs up
Tue Aug 2, 2016, 4:27 am

Re-use of excavated rocks onsite for construction.

NC-2009 MRc2:Construction Waste Management
posted by  Palak Varshney  on 

Project Location: India. The project construction site has rock bed. These rock are excavated, broken and re-used in construction on-site.

2
Default Avatar
LEEDuser Expert
472 thumbs up
Mon Aug 1, 2016, 9:33 am
2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Jul 11, 2016, 3:29 am

Minimum Energy Performance

EBOM-v4 EAp2:Minimum energy performance
posted by  Aqrab Ali Rana  on 

Dear All, I am working on a industrial project registered in Existing building Operation and maintenance located Out of US , that have its own electricity production of 4 Mw through gas engines a

2
Senior Sustainability Manager
WSP - Built Ecology
LEEDuser Expert
188 thumbs up
Thu Jun 30, 2016, 7:52 pm

Energy Simulation

NC-v4 EAp2:Minimum energy performance
posted by  Muzamil Rafique  on 

Hello Marcus, i want some clarification regarding HVAC Baseline and Proposed model.

8
Wed Jun 29, 2016, 4:44 pm

Energy Modeling

NC-v4 EAp2:Minimum energy performance
posted by  Muzamil Rafique  on 

Dear All, i am doing a energy simulation for bank building. software have no option LEED Rating V4. It have only LEED 2009 rating system.

8
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jun 23, 2016, 4:07 pm

Energy Modeling

NC-2009 EAp2:Minimum Energy Performance
posted by  Muzamil Rafique  on 

Hi Marcus, I am doing energy modelling for a Bank building. Total Building Area is 55,600 SFT.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jun 23, 2016, 3:26 pm