Dear all,
Hi.
For LEED NC
NC-2009 EAp2:Minimum Energy Performanceposted by Thais Inatomi on
Dear all, Hi. For LEED NC certification, I’m modeling a building with 03 floors and less than 14.000 m² conditioned floor area.
shgc Values
NC-2009 EAc1:Optimize Energy Performanceposted by TOMAS URIBE on
Hello Marcus. The fenestration supplier of a project gave us SHGC values from a simulation. We would like to know if it is acceptable for LEED simulation.
CitiBike- Bicycle Commuting SS c4-3
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Alfred Servodidio on
Our project in NYC has a Citi Bike location less than 200 yards from the entrance. The owner will pay for up to 80% of the annual cost for all employees.
Building Demolition
NC-2009 MRc1.1:Building Reuse—Maintain Existing Walls, Floors and Roofposted by Chris Eger on
We are demolishing a large building that is no longer in use and is twice the size of an existing portion being retained.
Using the calculator (continued)
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Christina Reeves on
Hello again, We now have the 62MZ spreadsheet working (thanks again!), but a few more questions have come up as our ME works through it. Can anyone provide some insight on these? 1.
Tenant Metering Questions
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Marina Andrade on
Hi, I'm working on a project that has many storage modules that will be occupied by tenants.
Rebar - Offsite Scrap Recycling
CS-2009 MRc2:Construction Waste Managementposted by Roberto Meza on
Hello, We have an interesting situation at a large project, Rebar is being bought from a company which at the same time offers to bend it into the various figures needed for columns etc.
EAp2 form issue on table 2-6
CS-2009 EAp2:Minimum Energy Performanceposted by charles bell on
Our project is a CS mixed use: hopefully this is not too general a question. We cannot get the table EAp2-6 to pull down results from the previous tables.
Cold, dark warehouse, round 3 (at least)
CS-2009 MRp1:Storage and Collection of Recyclablesposted by Tiffany Moore on
I just received review comments back on MRp1 that I simply can't validate. I'd appreciate any help or advice that might be out there.
Pool
NC-2009 SSc5.2:Site Development—Maximize Open Spaceposted by Jorge Lopez de Obeso on
If SSc2 is achieved, would a swimming pool count towards credit achievement? I´d think so, however I read other posts and there is a comment that says no... Does anyone have a positive feedback a